Weekly Road Reports
All Resurfacing and Patching works on hold, due to the Scord Quarry mixing plant being closed for maintenance. The opening times will be updated when available.
Pier Road, Walls
Resurfacing works due to begin on Monday 6th May that are expected to take 1 week to complete. The road will be closed between 9am and 3pm. Any queries regarding these works please contact John Duncan (744105)
Tumblin, Bixter
Resurfacing works to start on Tuesday 14th May that are expected to take 1 week to complete. The road will be closed between 9am and 3pm. Any queries regarding these works please contact John Duncan (744105)
Valleyfield to Parkgate
Hot tar patching works to begin on Thursday 9th May that are expected to take 1 week to complete. Traffic lights in operation so short delays can be expected. Any queries regarding these works please contact John Duncan (744105)
Burrafirth, Unst
Cold tar patching works to start on Thursday 9th May that are expected to take 2 days to complete. Short delays can be expected. Any queries regarding these works please contact John Duncan (744105)
Fetlar
Hot tar patching works to start on Wednesday 15th May that are expected to take 2 days to complete. Short delays can be expected. Any queries regarding these works please contact John Duncan (744105)
South Road, Lerwick
Surface dressing prep works are due to start on Monday 6th May and are expected to take 3 days to complete. Traffic lights will be in operation after 09.00. Any queries regarding these works please contact Barrie Scobie (744134)
Brig o’ Fitch
Surface dressing prep works are due to start on Thursday 9th May and are expected to last for 3 days to complete. Traffic lights will be in operation after 09.00. Any queries regarding these works please contact Barrie Scobie (744134)
A970 Cunningsburgh
Surface dressing prep works are due to start on 13th May and take 3 days to complete. Traffic lights will be in operation after 09.00. Any queries regarding these works please contact Barrie Scobie (744134)
BT Openreach, Scottish Water, Hydro and District Heating works.
>
BT Openreach, SSE and Scottish Water Works, Various Locations |
Location |
Expected End Date |
---|---|---|
Boothpark | Whalsay | 13/04/2024 |
U700 From Saltness Road To Symbister | Whalsay | 13/04/2024 |
A970 From Windy Grind (Old A971 Jcn) To Linkster Junction | Tingwall | 19/04/2024 |
A970 From Vatster Junction To Hamarsland Junction | Tingwall | 28/04/2024 |
Current Road Closures
No Current Road Closures
For Information on all road works happening in Shetland, Council and non Council Works, Please visit the Scottish Road Works Register.