Plan for and deliver a new Council Change/Renewal Programme
This is an area where we acknowledge further progress requires to be made. Audit Scotland, in their Best Value report said that, “To date, very little progress has been made on the Change Programme, with the PMO at the early stages of developing its remit and workplan. The process of identifying all existing projects across the Council, most of which pre-date the change programme, is ongoing. The programme is not currently transparent with the project timelines and available resources missing”. As part of the BVAR Improvement Plan, a new Project Officer has been recruited, the Change Programme has been further developed and will be reported to Committee for agreement.